This project was for the design, build and commissioning of the BOG Compressor House, the Fire Water Pump House, Pipe racks, misc steel amounting to approx 1800 te

Installation took place from August 2006 to February 2007.

Scope of work included design, detail design, fabrication, galvanising, cold rolled, cladding and louvres.

Internally applied Fendolite MII fire proofing, open grid access platforms, handrails, ladders, 3 No. overhead cranes,

Heating, Ventilation and Air Conditioning (HVAC), Electrical and control panels,

Roller shutter doors, access doors and temporary opennings.


   

   

        

          

       